The proposed water project’s current project schedule is shown below. The schedule will be updated as funding is obtained and the project develops, so please come back and check the most recent information.
Action | Date |
Contract with the EPA for Thriving Communities Funding | July 2025 |
Contract for Engineering Services | August 2025 |
Perform an engineering alternatives analysis and prepare a report. | November 2025 – April 2026 |
Preliminary and Final Design Phase | December 2025 – April 2026 |
Water PER to evaluate all water system issues, identify long-term projects and apply for funding for treatment system construction upgrades | January 2026 to May 2026 |
Complete Final Design – Submit to DEQ for Review | April 2026 |
Anticipated DEQ approval of Plans and Specifications | June 2026 |
The wastewater projects are currently in progress. The phase 1 wastewater project is in construction as of March 2025, and the phase 2 wastewater project is in the design and permitting stage of project development.